| 1. Customer concentration | Share of revenue from the largest customers | Revenue or concentration-of-risk note | CoreWeave: Microsoft ~67% of 2025 revenue (10-K); three unnamed customers 36%, 26%, 10% in Q2 2026 (10-Q). Nebius: three customers 24%, 21%, 14% (Q2 2026 interim financials) |
| 2. Debt and refinancing | Interest expense vs operating income; principal due in the next 12–18 months vs cash | Income statement; debt note (maturity table); liquidity section of MD&A | CoreWeave Q2 2026: $640M net interest vs −$49M operating loss; $10.6B due by end-2027; $7.5B of current debt vs $5.5B cash (10-Q). Nebius: $3.5B senior secured facility with a 364-day maturity (Oct 22, 2026) |
| 3. Interest rates | Change in interest cost per 1 percentage point; cost of the newest borrowing | Item 3, market-risk disclosures; debt note | CoreWeave: about $30M of quarterly interest per 1 point on floating-rate debt (10-Q); its 9.75% notes due 2031 traded at a 15.78% yield on Oct 15, 2026 (CNBC) |
| 4. GPU depreciation | Useful life of computing equipment; any change in estimate | Property and equipment note; accounting-policy note | CoreWeave: six years since 2023 (10-K). Nebius: four to five years from Jan 1, 2026, cutting expected 2026 depreciation by ~$167.6M (20-F). Amazon shortened part of its servers to five years in 2025 |
| 5. Power and construction delays | Active vs contracted power; delivery dates vs the original schedule | MD&A business update; 8-Ks on lease amendments | CoreWeave: 1.5 GW active vs ~3.7 GW contracted (Jun 30, 2026). Cipher: two Barber Lake data halls’ rent start moved from Q4 2026 to Q4 2026–Q1 2027 (8-K, Oct 13, 2026) |
| 6. Dilution | Change in share count; convertible notes outstanding; at-the-market programs | Equity note; debt note (converts); subsequent events | CoreWeave: $3.0B of new equity in H1 2026 (10-Q) and $4.2B of 2.875% convertible notes due 2033 (8-K, Sep 22, 2026). Cipher: $850M of 0% convertible notes offered (8-K, Oct 13, 2026) |
| 7. Contract terms | Take-or-pay share; term; “up to” amounts; extension options; prepayments | Remaining performance obligations note; risk factors | CoreWeave: take-or-pay committed contracts of 1–6 years were 98% of Q2 2026 revenue; RPO $103.7B can change with credits and delivery delays (10-Q). Nebius–Meta: “up to” ~$27B, of which up to $15B depends on unsold capacity (Mar 16, 2026) |
| 8. Competition and consolidation | New capacity from customers themselves; pricing per GPU hour; consolidation | Risk factors; management commentary | Microsoft, Alphabet, Amazon and Meta plan about $725–745B of 2026 capital spending, much of it their own data centers (company guidance, Oct 22, 2026). Gartner forecast on Oct 14, 2026 that over 80% of neocloud providers will cease independent operations by 2030 |