# Bitcoin Miners’ AI Pivot: How Miners Became AI Data-Center Hosts

> IREN, Cipher, TeraWulf, Hut 8, Core Scientific, Galaxy, Riot and Applied Digital now earn more from AI tenants than from mining, or have signed AI contracts worth billions over 12 to 20 years. Here is why power made the switch possible, every disclosed contract with its date, the two business models, and where the risks sit.

Source: https://www.exent.ai/resources/bitcoin-miners-ai-pivot · Reviewed by David, Senior Analyst, Exent · Published Nov 13, 2026 · Updated Nov 13, 2026

## Key takeaways

- Bitcoin miners became AI hosts because they already control what AI data centers lack most: grid connections, land and experience running large power loads. They rent that power to AI companies under 12- to 20-year leases or, like IREN, fill it with their own GPUs.
- The switch shows in revenue: in the quarter to September 30, 2026 Core Scientific earned $215.4M from AI colocation against $17.4M from mining, TeraWulf $63.0M from AI leases against $13.2M from mining, and IREN $200M from AI cloud against $28M from bitcoin (company releases, November 2026).
- Contracts are large and long: Riot with an unnamed AI lab 910 MW for 15 years (~$28B, November 2026) on top of 191 MW for 20 years (~$9.1B), TeraWulf–Anthropic ~401 MW for 20 years (~$19B), Cipher–AWS 300 MW for 15 years (~$5.5B), Galaxy and Core Scientific with CoreWeave. Contracted is not yet revenue: Riot targets 400 MW at Corsicana for September 2027 and the first 96 MW under its Rockdale lease for December 2027.
- Worked example: a 20-year AI lease pays about $2.4M per MW a year (Riot and TeraWulf filings); TeraWulf’s guided build cost of $8–10M per MW equals roughly 3.4–4.2 years of that gross rent, before running and financing costs. That is a revenue-to-capex illustration, not a cash payback.
- The risks are execution (amended delivery dates), financing (convertibles, interim loans) and single tenants, some of which are themselves neoclouds. These stocks fell 18%–50% from Sep 30 to Oct 23, 2026 (Exent market data).

## Why are bitcoin miners turning into AI data-center hosts?

Because power, not chips, became the scarce input for AI data centers, and miners already had it. A bitcoin mine is a building full of computers drawing tens to hundreds of megawatts from the grid; an AI data center needs the same grid connection, substations and land, plus cooling for far denser racks. A miner that can deliver a powered building years before a new site could be connected can rent it to an AI company under a long contract, which gives a powered site another use besides mining. TeraWulf’s CEO put it in the company’s Q2 2026 release: “access to power becomes the defining constraint on AI infrastructure.” Riot describes its edge as “multi-gigawatt-scale power capacity that is already fully approved and energized” (company claims, August 2026).

The pivot is not new for the industry’s largest name: CoreWeave itself began in 2017 as a crypto-mining venture (CNBC). What is new is the scale: the ledger below uses contracts and expansions disclosed in 2025 or 2026, most of them for 12 to 20 years. Scope: US-listed companies that mine or mined bitcoin, or hosted miners, and now lease data-center capacity to AI customers or run their own GPU cloud, using each company’s latest filing as of November 9, 2026. Excluded: private hosts, chip suppliers and crypto prices. This is education, not a recommendation on any stock.

**Two ways a miner earns from AI**

What the miner already has:
- Grid power (contracted MW, substations)
- Land and sites (often rural, near power)

What it builds:
- Powered AI building (cooling, IT halls; $8–10M per MW (TeraWulf guide))
- Own GPUs (IREN model) (chips bought with loans and prepayments)

Who pays:
- Tenant pays rent (12–20 year lease: AWS, Anthropic, CoreWeave, AMD)
- Customer pays per GPU hour (3–5 year contracts: Microsoft)

Flows:
- Grid power → Powered AI building: energize
- Powered AI building → Tenant pays rent: landlord model
- Own GPUs (IREN model) → Customer pays per GPU hour: GPU cloud model

*Simplified. In the landlord model the tenant owns the GPUs and their obsolescence risk; in the GPU cloud model the miner does.*

## Which bitcoin miners have signed AI contracts? (dated ledger)

At least eight listed miners or mining hosts have signed AI leases or GPU contracts with disclosed values. The ledger lists each as the company states it. Values are company-defined (initial term, “potential”, or with extensions) and MW are critical IT unless marked gross, so the rows are not additive. How these contract measures differ is explained in [backlog, RPO and ARR](https://www.exent.ai/resources/backlog-rpo-arr-explained).

| Company | Customer | Capacity | Term | Value as disclosed | Disclosed |
| --- | --- | --- | --- | --- | --- |
| IREN (GPU cloud) | Microsoft | GPU capacity at Childress, Texas | Five-year average | ~$9.7B, 20% prepaid | 8-K, Nov 3, 2025 |
| IREN (GPU cloud) | NVIDIA | GPU capacity | Five years | ~$3.4B | 10-K, Aug 27, 2026 |
| Cipher Digital | Amazon Web Services | 300 MW | 15 years | ~$5.5B | 8-K, Nov 3, 2025 |
| Cipher Digital | Fluidstack, then a leading AI lab (unnamed) for a second 10-year term | Barber Lake campus | 20 years (10 + 10) | Over $9B after amendment (was $3.8B) | 8-K, Sep 25, 2026 |
| TeraWulf | Anthropic | ~401 MW | 20 years | ~$19B initial term (up to ~$33B with extensions) | 8-K, Jul 6, 2026 |
| TeraWulf | Fluidstack (Google credit support $600M) | Lake Mariner halls | Not stated here | Not stated here | Q2 2026 results, Aug 5, 2026 |
| Riot Platforms | The same frontier AI lab (unnamed), Corsicana | 910 MW | 15 years | ~$28B (~$54B with options) | Q3 2026 results, Nov 4, 2026 |
| Riot Platforms | A frontier AI lab (unnamed), Rockdale | 191 MW | 20 years, to Jun 2048 | ~$9.1B (~$16.1B with options) | Q2 2026 results, Aug 10, 2026 |
| Riot Platforms | AMD | 50 MW (1,151 MW with both AI lab leases) | Not stated here | ~$38B combined with both AI lab leases | Jan 16 and Nov 4, 2026 |
| Core Scientific | CoreWeave | ~590 MW | 12 years | $10.2B | 8-K, Feb 26, 2025 |
| Core Scientific | AMD | ~530 MW (up to 2.5 GW) | 15 years | >$14B potential base revenue | Q2 2026 results, Jul 28, 2026 |
| Galaxy | CoreWeave (Helios) | 526 MW (800 MW gross) | 15-year base | $1.2B+ average annual revenue | Q2 2026 results, Aug 5, 2026 |
| Hut 8 | A high-investment-grade company (unnamed), Beacon Point Phase 2 | 352 MW IT (704 MW with Phase 1) | 15-year base | ~$9.8B base term (~$19.6B campus) | 8-K, Jul 20, 2026 |
| Hut 8 | Fluidstack (River Bend) and the unnamed Beacon Point tenant | 949 MW contracted (all leases) | Base terms | ~$26.6B aggregate base-term value | 8-K, Jul 20, 2026; Q3 2026 results, Nov 4, 2026 |
| Applied Digital | CoreWeave (Polaris Forge 1) | 400 MW | ~15 years | ~$11B | 8-K, Aug 29, 2025 |

Notes: Riot’s AMD lease began with 25 MW delivered by June 2026 and a second 25 MW under construction; the 1,151 MW and ~$38 billion combined figures are Riot’s (November 4, 2026), and Riot says the Corsicana tenant is the same lab that leased Rockdale. Corsicana is a powered land lease: Riot delivers land, power and pads, and the tenant installs and owns the modular compute buildings. Hut 8’s Beacon Point tenant signed both phases; its 949 MW and ~$26.6 billion totals include Phase 2. Cipher’s Barber Lake value combines the amended Fluidstack lease and a second 10-year term with a leading AI lab; its company-wide contracted revenue was $16.6 billion and its operating plus contracted capacity 907 MW (gross basis) at September 30, 2026. After September 30, 2026 IREN reported a five-year contract at about $22 million of estimated annual revenue per MW, with contractual customer prepayments covering 90% of estimated GPU capex, and an expanded contract with a frontier AI lab, without total values (November 5, 2026). Applied Digital is a hosting company rather than a miner: its older business rents powered space to crypto-mining customers (106 MW in Jamestown and 180 MW in Ellendale, North Dakota). Core Scientific’s planned merger with CoreWeave was terminated on October 30, 2025. Who CoreWeave is as a tenant is covered in [who are CoreWeave’s customers](https://www.exent.ai/resources/who-are-coreweaves-customers).

## How much of their revenue already comes from AI?

For four of them, most of it (Core Scientific, TeraWulf, IREN and Applied Digital); for the rest, the contracts are still mostly ahead. Quarter to September 30, 2026 (Applied Digital: August 31, 2026, its fiscal Q1 2027), the latest reported as of November 9, 2026; GAAP revenue as each company splits it (unaudited quarterly figures):

| Company | Quarter ended | AI / data-center revenue | Mining or mining-hosting revenue | Historical comparison |
| --- | --- | --- | --- | --- |
| Core Scientific | Sep 30, 2026 | $215.4M colocation (92.5% of $232.9M), including $57.6M of power and fuel fees passed through to the customer | $12.3M self-mining + $5.2M hosted mining | Quarter to Sep 30, 2025: colocation $15.0M, self-mining $57.4M (of $81.1M) |
| TeraWulf | Sep 30, 2026 | $63.0M HPC leases (83% of $76.2M) | $13.2M digital assets | Quarter to Sep 30, 2025: $50.6M = $43.4M mining + $7.2M HPC |
| IREN | Sep 30, 2026 (fiscal Q1 2027) | $200M AI cloud (88% of $228M; includes $65M booked as lease revenue) | $28M bitcoin mining | Quarter to Sep 30, 2025: AI cloud $7M, mining $233M |
| Applied Digital | Aug 31, 2026 (fiscal Q1 2027) | $262.6M HPC hosting: $65.8M base rent, $183.5M tenant fit-out services, $13.3M tenant recoveries | $37.8M hosting for crypto miners | Quarter to Aug 31, 2025: no HPC rent |
| Riot Platforms | Sep 30, 2026 | $18.4M data center: $7.7M base rent, $0.5M variable, $10.2M tenant fit-out reimbursement (10% of $181.4M) | $116.0M bitcoin mining (plus $47.0M engineering) | Quarter to Sep 30, 2025: mining $160.8M, engineering $19.1M (of $180.2M) |
| Galaxy | Sep 30, 2026 | $79.1M data-center leasing (first full quarter of 133 MW for CoreWeave) | Not comparable (trading and digital-asset business) | None a year earlier; $18.9M in the quarter to Jun 30, 2026 |
| Cipher Digital | Sep 30, 2026 | $5.9M HPC leasing (first rent, Black Pearl) | $20.8M bitcoin mining (of $26.7M) | Quarter to Sep 30, 2025: $71.7M, all mining |
| Hut 8 | Sep 30, 2026 | $1.4M colocation; AI-only revenue not separately disclosed; its 50% King Mountain venture’s $26.9M sits outside revenue | Mixed Compute revenue, not a mining-only figure: $68.4M (ASIC compute, AI cloud and traditional cloud combined); plus $1.3M Power revenue, $71.1M total | Quarter to Sep 30, 2025: $83.5M total |

Read the table with care. Periods differ: Applied Digital’s quarter ends August 31, 2026, the others September 30, 2026. The categories mix rent with reimbursements, fit-out services and other businesses, so the rows are not comparable measures of recurring AI rent. Totals may differ due to rounding.

Watch the GAAP net income lines with care too: several of these companies book large non-cash swings from revaluing warrants as their share prices move. TeraWulf booked a $755.7 million loss on that line in Q2 2026 and a $728.4 million gain in Q3 2026; Core Scientific’s Q3 2026 net income of $1.2 billion came mainly from the same effect. That swamps the operating picture. A side-by-side with debt and cash is in [neocloud stocks compared](https://www.exent.ai/compare/neocloud-stocks-compared).

## Hosting vs running your own GPU cloud: which model is riskier?

AI contracts offer another use for powered sites. The landlord rents out power and buildings for longer and leaves the chips to its tenant; GPU ownership adds hardware-obsolescence and financing exposure. These figures do not establish which model is more profitable or riskier overall. Worked example from the filings (our arithmetic, simplified):

| Step | Landlord (lease) | GPU cloud (IREN) |
| --- | --- | --- |
| Contract revenue per MW | Riot: $9.1B ÷ 191 MW = $47.6M over 20 years. TeraWulf: $19B ÷ 401 MW = $47.4M over 20 years | IREN: “>$20m revenue per MW (IT)” on recent three-year contracts (August 2026); “~$22 million per IT-MW” on a five-year contract signed after September 30, 2026 (company) |
| Revenue per MW: basis and period | Average per year over the initial term: $47.6M ÷ 20 = $2.38M (Riot); $47.4M ÷ 20 = $2.37M (TeraWulf) | About $22M estimated annual revenue per IT MW on IREN’s November 2026 five-year contract (its definition; not a lifetime lease value) |
| Upfront cost | Building and power fit-out: $8–10M per critical IT MW (TeraWulf guidance) | Building plus GPUs; customer prepayments covered 45–55% of GPU capex on recent contracts (August 2026); on the new five-year contract, contractual customer prepayments cover 90% of estimated GPU capex (IREN) |
| Gross revenue-to-capex illustration (not comparable payback measures) | $8M ÷ $2.37M = 3.4 years; $10M ÷ $2.37M = 4.2 years of gross rent, before running costs, interest and tax | “~2 year payback” on the three-year contracts (IREN’s own definition, August 2026; not the same measure) |
| Who owns the chips when they age | The tenant | IREN (depreciated over five years) |

Interpretation (ours): the lease turns a miner into something closer to a utility-like landlord whose risk is the tenant’s credit and the build schedule; the GPU cloud is a bet that rental prices hold while the chips lose value. Whether five or six years is a realistic life for an AI chip is its own argument, set out in [how long AI GPUs last](https://www.exent.ai/resources/gpu-depreciation-debate). Limits of the example: the $8–10M per MW is TeraWulf’s guidance for its own builds, not Riot’s; the IREN figure is the company’s own estimate; neither column includes power, staffing, interest or tax, so neither is a cash payback and the two columns are not directly comparable.

A third, lighter model arrived in November 2026: Riot’s Corsicana lease is a powered land lease, where Riot delivers land, power and pads and the tenant installs its own modular buildings (Riot funds $2 million per MW of site and electrical work and reimburses the tenant $4 million per MW for those buildings, per the release). On Riot’s figures that is about $28 billion ÷ 910 MW ÷ 15 years ≈ $2.05 million per MW a year, against about $6 million per MW of capital. Capital divided by average annual contract revenue, undiscounted, is about 2.9 years (our arithmetic, same limits as above); this is not a cash payback forecast, and spending, delivery and rent are phased. Riot itself cites an unlevered yield on cost of about 33%. Less rent per MW than a full building lease, but for well under the $8–10 million per MW of a full build.

## What are the risks in the miner-to-AI pivot?

Three risks show up in the filings already, each with a dated example.

| Risk | Dated example | What to check |
| --- | --- | --- |
| Execution: building on time and on budget | Cipher amended its Barber Lake lease on Sep 25, 2026: data halls are now due from Q4 2026 through Q1 2027 (rent starts as each is delivered; its Oct 13 presentation shows halls 3–4 moved from Q4 2026), and Cipher bears the first $359.3M of costs above the original budget, with the tenant repaying half of any excess beyond that as rent. IREN moved its >$4B annualized revenue target from year-end 2026 to January 2027, possibly February (Nov 5, 2026). TeraWulf now expects Anthropic’s halls to be completed from late 2027 through Q2 2028 (Nov 6, 2026), after guiding to the full 401 MW “by early 2028” in July. Riot’s first 96 MW of its Rockdale lease are due in December 2027 | Delivery dates vs the original lease; rent credits; cost estimates in each quarterly update |
| Financing: who pays for the build | Riot arranged a $573M interim facility while an investment-grade backstop is finalized (Aug 10, 2026). Galaxy priced $3.5B of 9.875% secured notes for Helios (Jul 23, 2026). Cipher priced $850M of 0% convertible notes (Oct 14, 2026). TeraWulf signed Google credit support for the debt behind its Anthropic lease (Nov 4, 2026). Hut 8 reports $7.5B of investment-grade project financing | Secured vs unsecured; recourse to the parent; convertibles and new shares that dilute holders |
| Single tenants, some of them neoclouds | TeraWulf’s largest lease is one tenant (Anthropic). Riot’s two AI lab leases (1,101 of its 1,151 MW) are with the same unnamed lab, and Hut 8’s Beacon Point (704 MW) with one unnamed tenant. Galaxy’s Helios, Applied Digital’s Polaris Forge 1 and Core Scientific’s ~590 MW are leased to CoreWeave | Tenant share of contracted value; tenant credit rating; credit support such as Google’s $600M for Fluidstack at TeraWulf |

The market priced these risks hard in October 2026: from September 30 to October 23 Cipher fell 49.8%, Riot 37.8%, Galaxy 35.4%, Hut 8 28.9%, Applied Digital 25.1%, TeraWulf 23.5% and Core Scientific 18.0% (Exent market data). What is documented about why is in [why neocloud stocks fell in October 2026](https://www.exent.ai/resources/neocloud-selloff-october-2026); the full risk checklist with the 10-Q lines to read is in [investing in neoclouds: the risks](https://www.exent.ai/resources/investing-in-neoclouds-risks).

## When is the miner-to-AI story wrong, and who should not use it?

The bullish reading is wrong when “contracted” is read as “earned”: Riot reports about $9.1 billion of contracted revenue over the 20-year initial term of its Rockdale lease, starting in late 2027, and about $28 billion over 15 years at Corsicana from September 2027 at the earliest, both subject to delivery and the tenant paying; TeraWulf’s “up to $33 billion” depends on Anthropic exercising two options, and Core Scientific calls its $24 billion “potential” contracted revenue. It is also wrong when a lease is treated as risk-free: a landlord whose tenant is CoreWeave carries part of CoreWeave’s risk. The bearish reading is incomplete when it treats these companies as pure bitcoin bets: at Core Scientific, TeraWulf and IREN, mining is now the smaller share of revenue. That alone does not show that the stocks move less with bitcoin.

Who should not use this page to pick a stock: anyone looking for crypto exposure (a miner with AI leases is increasingly a real-estate and credit story; see [bitcoin in a portfolio](https://www.exent.ai/resources/bitcoin-in-portfolio) and crypto-stock correlation for that question), or anyone who cannot hold a stock through a 50% fall. This comparison does not show which stock or position size suits an investor; how sizing is usually thought about is in [how big a speculative sleeve should be](https://www.exent.ai/resources/speculative-sleeve-size).

- Limitations: contract values and MW are company-defined and measured differently (critical IT vs gross MW; initial term vs with options); rows are not additive.
- Revenue splits are each company’s latest quarter (to September 30, 2026; Applied Digital to August 31, 2026), unaudited quarterly figures; IREN reports in rounded millions. The next quarter ends December 31, 2026 (Applied Digital: November 30, 2026).
- Tenants are named only where the company named them; press reports about unnamed tenants are not used.
- The per-MW example is simplified arithmetic on two leases and one company’s cost guidance; it is not a valuation.
- Stock moves are Exent market data to October 23, 2026; past moves do not predict future ones.

## Add market context with Exent Market intel

Market intel provides market context, cross-asset analysis, an events calendar and regular written notes. These can inform your review of an existing plan; they do not reliably predict crashes or guarantee better outcomes.

1. Regular written notes that read cross-asset ratios, including bitcoin vs gold and high-beta vs low-volatility stocks: the two kinds of risk appetite these companies sit between.
2. An events calendar with earnings dates and Fed meetings, so each company’s next quarterly update is on your radar.
3. A reading of US market risk (Risk ON, Neutral or Risk OFF) built on four pillars, with an email when the reading changes.

Exent is our product: [Exent Market intel](https://www.exent.ai/intel)

## Frequently asked questions

### Why are bitcoin miners pivoting to AI?

Because they control grid power and sites, the scarcest inputs for AI data centers, and 12–20 year AI leases give those powered sites another use besides mining. In the quarter to September 30, 2026 Core Scientific made $215.4M from AI colocation and $17.4M from mining.

### Which bitcoin miners have AI contracts?

Disclosed contracts include IREN with Microsoft (~$9.7B), Cipher with AWS (~$5.5B, 15 years), TeraWulf with Anthropic (~$19B, 20 years), Riot with an unnamed AI lab (~$9.1B over 20 years, plus ~$28B over 15 years signed November 2026), Core Scientific with CoreWeave and AMD, Galaxy with CoreWeave and Hut 8 (~$26.6B base-term value, including a $9.8B Beacon Point lease in July 2026).

### What is the difference between IREN and TeraWulf?

IREN owns GPUs and sells computing time (GPU cloud), so it carries chip obsolescence risk; TeraWulf leases powered buildings to tenants such as Anthropic and Fluidstack (landlord), so the tenant owns the chips. In the quarter to September 30, 2026 IREN’s AI cloud revenue was $200M and TeraWulf’s lease revenue $63.0M.

### Is Applied Digital a bitcoin miner?

No. It hosts other companies’ mining machines (286 MW in North Dakota) and builds AI campuses leased to CoreWeave and hyperscalers, with about $36B of contracted revenue over initial terms as of Aug 31, 2026.

### Who is Riot’s AI tenant?

Riot has not named it; its August 10, 2026 release calls it a leading frontier AI lab. The 20-year lease covers 191 MW of critical IT capacity and about $9.1B over the initial term, with the first 96 MW due in December 2027. On November 4, 2026 Riot said the same lab signed a 15-year lease for 910 MW at Corsicana, about $28B over the initial term.

### How much does an AI lease pay per megawatt?

In the Riot and TeraWulf 20-year leases, about $47M of contract value per MW, or roughly $2.4M per MW per year (our arithmetic on company figures). GPU clouds earn more per MW but must buy the chips.

### Are bitcoin miner stocks still tied to the bitcoin price?

Mining is now a smaller share of revenue at the ones with large AI leases: in the quarter to September 30, 2026 it was $13.2M of $76.2M at TeraWulf, $17.4M of $232.9M at Core Scientific and $28M of $228M at IREN. That alone does not show that the stocks move less with bitcoin. Miners without leases remain mainly bitcoin businesses.

### Who owns the GPUs in a miner’s AI lease?

Usually the tenant. In the landlord model the miner delivers the powered building and the tenant, such as CoreWeave or AWS, owns the chips and their obsolescence risk; IREN is the exception, buying its own GPUs and depreciating them over five years.

## Sources

1. [IREN Reports FY26 Results (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1878848/000187884826000051/irenreportsfy26results.htm) — IREN (SEC), 2026-08-27
2. [Form 8-K: Microsoft contract](https://www.sec.gov/Archives/edgar/data/1878848/000114036125040072/ef20058139_8k.htm) — IREN (SEC), 2025-11-03
3. [Form 10-K for the fiscal year ended June 30, 2026](https://www.sec.gov/Archives/edgar/data/1878848/000187884826000052/iren-20260630.htm) — IREN (SEC), 2026-08-27
4. [Cipher Mining provides third quarter 2025 business update (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1819989/000181998925000110/nov3_earningspressreleasex.htm) — Cipher Digital (SEC), 2025-11-03
5. [Project Compass investor presentation (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1819989/000119312526419743/d134900dex991.htm) — Cipher Digital (SEC), 2026-10-13
6. [Cipher Digital expands Barber Lake lease term to 20 years (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1819989/000181998926000043/barberlakeleaseamendmentpr.htm) — Cipher Digital (SEC), 2026-09-25
7. [Pricing of $850.0 million of 0.00% convertible senior notes due 2032 (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1819989/000119312526421035/d77312dex991.htm) — Cipher Digital (SEC), 2026-10-14
8. [Cipher Digital provides third quarter 2026 business update (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1819989/000181998926000047/exh991-q326_earningsxprxvf.htm) — Cipher Digital (SEC), 2026-11-02
9. [IREN Reports Q1 FY27 Results (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1878848/000187884826000065/irenreportsq1-fy27result.htm) — IREN (SEC), 2026-11-05
10. [Form 10-Q for the quarter ended September 30, 2026](https://www.sec.gov/Archives/edgar/data/1878848/000187884826000066/iren-20260930.htm) — IREN (SEC), 2026-11-05
11. [TeraWulf announces Anthropic lease at Justified Data campus (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1083301/000110465926080583/tm2619468d1_ex99-1.htm) — TeraWulf (SEC), 2026-07-06
12. [TeraWulf secures Google credit backstop for Anthropic lease financing (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1083301/000162828026069810/wulfhawesvillecsaandepcmpr.htm) — TeraWulf (SEC), 2026-11-04
13. [TeraWulf Reports Third Quarter 2026 Results (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1083301/000162828026071306/a_wulfearningsreleaseq32026.htm) — TeraWulf (SEC), 2026-11-06
14. [Hut 8 fully commercializes Beacon Point with second 352 MW lease (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1964789/000110465926084862/tm2620835d1_ex99-1.htm) — Hut 8 (SEC), 2026-07-20
15. [Hut 8 reports third quarter 2026 results (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1964789/000110465926122347/tm2628741d1_ex99-1.htm) — Hut 8 (SEC), 2026-11-04
16. [Core Scientific Announces Third Quarter 2026 Results (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1839341/000183934126000028/q32026corescientificinc-ea.htm) — Core Scientific (SEC), 2026-11-05
17. [Galaxy prices $3.507 billion of senior secured notes (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1859392/000185939226000074/exhibit991-pressreleasepri.htm) — Galaxy Digital (SEC), 2026-07-23
18. [Galaxy third quarter 2026 results (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1859392/000185939226000108/glxy-20260930xpressrelease.htm) — Galaxy Digital (SEC), 2026-10-27
19. [Riot Platforms Reports Third Quarter 2026 Financial Results and Strategic Highlights (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1167419/000110465926122368/riot-ex99d1.htm) — Riot Platforms (SEC), 2026-11-04
20. [TeraWulf Reports Second Quarter 2026 Results](https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results) — TeraWulf, 2026-08-05
21. [Hut 8 reports second quarter 2026 results](https://www.hut8.com/news-insights/press-releases/hut-8-reports-second-quarter-2026-results) — Hut 8, 2026-08-04
22. [Core Scientific Announces Second Quarter 2026 Results](https://investors.corescientific.com/news-events/press-releases/detail/139/core-scientific-announces-second-quarter-2026-results) — Core Scientific, 2026-07-28
23. [Core Scientific and CoreWeave lease expansion (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1839341/000162828025008312/ex991-coreweavepressrelease.htm) — Core Scientific (SEC), 2025-02-26
24. [Core Scientific terminates merger agreement (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1839341/000114036125039808/ef20057995_ex99-1.htm) — Core Scientific (SEC), 2025-10-30
25. [Galaxy second quarter 2026 results](https://www.sec.gov/Archives/edgar/data/1859392/000185939226000084/glxy-20260630xpressrelease.htm) — Galaxy Digital (SEC), 2026-08-05
26. [Riot Platforms Reports Second Quarter 2026 Financial Results and Strategic Highlights](https://www.riotplatforms.com/riot-platforms-reports-second-quarter-2026-financial-results-and-strategic-highlights/) — Riot Platforms, 2026-08-10
27. [Fiscal first quarter 2027 results (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1144879/000114487926000057/0001144879-26-000057.txt) — Applied Digital (SEC), 2026-10-07
28. [Applied Digital finalizes additional 150MW lease with CoreWeave (Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1144879/000149315225012458/ex99-1.htm) — Applied Digital (SEC), 2025-08-29
29. [CoreWeave’s market confidence erodes as bond yields spike and stock sinks](https://www.cnbc.com/2026/10/21/coreweaves-market-confidence-erodes-as-bond-yields-spike-stock-sinks.html) — CNBC, 2026-10-21

---

Educational content, not investment advice. Past performance does not guarantee future results.